Construction Planning & Management Mcqs Start Creating PDF
Construction Planning & Management Mcqs, this topic has 87 mcqs, It takes five to ten minutes to complete this free construction planning & management mcqs test. You will see 4 or 5 option of each question. You must choose / think only one option and then press on answer key for check right answer. Practice "construction planning & management mcqs" MCQs and share with your friends, brothers, sisters.
construction planning & management mcqs (Total Quiz: 87)
MCQ: Select the incorrect statement________?
- A critical path always begins at the very first event
- A critical path always terminates at the last event
- Critical activities control the project duration
- Critical activity is the one for which free float is zero
D
MCQ: Select the incorrect statement______?
- Start float and finish float are always equal
- Total float can be either start float or finish float
- Start float and finish float need not be equal
- Start float and finish float are the differences between activity times and not event times
C
MCQ: Select the incorrect statement_______?
- Earliest start of an activity is the early event time of the node it leaves
- Latest finish of an activity is the late event time of the node it enters
- Latest start of an activity is its latest finish minus its duration
- none of the above
D
MCQ: Select the correct statement_______?
- Activity arrows in a CPM network are drawn to scale
- The tail of an arrow represents the finish of an activity
- Arrow bead represents the start of an activity
- none of the above
D
MCQ: PERT technique of network analysis is mainly useful for__________________?
- small projects
- large and complex projects
- research and development projects
- deterministic activities
C
MCQ: In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
- normal distribution curve
- Poisson’s distribution curve
- Beta – distribution curve
- none of the above
C
MCQ: Earliest finish of an activity is always_______________?
- greater than earliest event time of the following node
- less than earliest event time of the following node
- less than or equal to earliest event time of the following node
- greater than or equal to earliest event time of the following node
C
MCQ: In the network shown in Fig. (15 fig) the latest start time of an activity 4-5 is_________________?
- 2
- 4
- 8
- 7
B
MCQ: If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
- 3.5 and 5/6
- 5 and 25/36
- 3.5 and 25/36
- 4 and 5/6
C
MCQ: Free float is mainly used to_________________?
- identify the activities which can be delayed without affecting the total float of preceding activity
- identify the activities, which can be delayed without affecting the total float of succeeding activity
- establish priorities
- identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
B